Status model
Project and issue statuses, entry rules, labels and names.
This file is the single source for statuses, entry rules and labels. The guide and the skills link here. A status has an entry rule. Move an item to a status only when the rule is true.
Project statuses
One project = one PRD.
| Status | Linear type | Entry rule |
|---|---|---|
| Shaping | Backlog | The PRD or brief is in draft or in review |
| Ready | Planned | The PRD is approved. Stories meet the Definition of Ready |
| Building | Started | The first story started |
| Measuring | Started | Shipped. The Metric check-in milestone has a date |
| Done | Completed | /ship-review wrote the verdict in the PRD |
| Paused | Paused | The decision is logged in PRD §11 |
| Canceled | Canceled | The decision is logged in PRD §11 |
Issue statuses
One issue = one user story.
| Status | Linear type | Entry rule |
|---|---|---|
| Triage | Triage | Inbound: a client request, a bug, or work found with no issue. Nobody accepted it yet |
| Backlog | Backlog | Accepted, not scheduled. Add the label Needs clarification if the story is not clear |
| Todo | Unstarted | Meets the Definition of Ready. A person or an agent can start it |
| In Progress | Started | Work started |
| In Review | Started | A PR is open, or design is in review. The GitHub integration moves it |
| Verify | Started | Someone other than the builder checks the acceptance criteria. /qa works here |
| Done | Completed | The acceptance criteria pass |
| Canceled | Canceled | Closed without delivery. Linear duplicates go here |
There is no "Blocked" status. Use the Linear "blocked by" relation. The saved view "Blocked" filters on the relation.
Definition of Ready (entry rule for Todo)
A story enters Todo only when it has all of these:
- The requirement IDs it implements (
R-n) and a link to the PRD. - Acceptance criteria that a person can test, with at least one failure path.
- A link to the design frames, with the states covered.
- The events it must emit, if the PRD has metrics for it.
- The repo or surface where the work happens.
- A way to verify it: the environment and the steps or the test.
- A named verifier, who is not the builder.
Definition of Done (entry rule for Done)
A story moves from Verify to Done only when someone other than the builder verified each acceptance criterion. An agent cannot verify work that it built.
Labels
| Group | Applies to | Values |
|---|---|---|
| Discipline | Issue | Design, Engineering, Product, Content |
| Clarity | Issue | Needs clarification |
| Document type | Project | PRD, Brief, No-PRD (ops or maintenance projects) |
| Area | Project | From the client profile. For example F0 Marketing … F5 Partners, Platform |
| Track | Project | Track, only for parallel tracks of one PRD |
| Iteration | Project | Use Linear cycles if the team uses them. If not, IT.n |
Names
| Thing | Pattern | Example |
|---|---|---|
| Project | [Client] / [Area] / [Scope]. Add / V02 only for a second version | Reloca / F4 HR / Recruiter pipeline |
| PRD document | PRD · [project name] | PRD · Reloca / F4 HR / Recruiter pipeline |
| Milestone | Phase name. Defaults: Foundation, Enhancement, Polish | Foundation |
| Last milestone | Metric check-in, with the date from PRD §8 | |
| Requirement | R-n | R-3 |
Old → new mapping (migration only)
| Old project status | New |
|---|---|
| Backlog | Shaping (PRD not approved) or Ready (PRD approved) |
| Planned | Ready |
| In Progress, Ready to QA, In QA | Building |
| Completed | Measuring (no ship-review yet) or Done (ship-review done) |
| Archived (custom status) | Done, then use Linear archive |
| Canceled | Canceled |
| Old issue status | New |
|---|---|
| To be clarified | Backlog + label Needs clarification |
| Backlog, Todo, In Progress, In Review, Done, Canceled | Same name |
| Ready 4 QA, In QA | Verify |
| Blocked | The status before the block, plus a "blocked by" relation |
| Duplicate | Canceled (Linear duplicate flow) |