2. How work moves
One scope from idea to verdict, step by step, with its variations.
One example, from idea to verdict. The client and the numbers are invented.
The trigger. Research for the client Acme shows that recruiters lose candidates because they cannot mark the good ones in the pipeline view. The study is ACM-2610.
| # | Step | What happens in the example | Project status |
|---|---|---|---|
| 1 | Start | Ana (product) runs /prd. The skill interviews her: whose problem, what evidence, what is out of scope. It challenges a claim that has no data and records it as an open question | — |
| 2 | Draft | The skill writes the PRD. Ana confirms. The skill creates the project Acme / F4 HR / Candidate flags with the PRD as its document, a summary, and the milestones Foundation (20 Jan) and Metric check-in (20 Feb) | Shaping |
| 3 | Review | Design and the engineering lead read the PRD and comment in the document. Ana presents it to the client and logs the result in §11. One open question blocks the build. She resolves it | Shaping |
| 4 | Approve | The reviewers sign off. Ana tells /prd that the PRD is approved | Ready |
| 5 | Break down | Ana and Bo (design) run /to-issues Foundation. The skill proposes 6 stories. Each cites its requirements (R-1, R-2…). They merge two stories and approve. 4 stories are complete and go to Todo. 1 has no design frames yet and goes to Backlog with Needs clarification | Ready |
| 6 | Build | Cy (engineering) starts the first story. The branch name contains the issue ID, so the open PR moves the story to In Review, and the merge moves it to Verify. At the end of each day, Cy runs /eod-sync: it drafts the comments and links, Cy confirms | Building |
| 7 | Verify | Bo is the verifier of the story. Bo runs /qa. It checks each acceptance criterion on the test environment and posts the result. All pass. Bo confirms, and the story goes to Done | Building |
| 8 | Ship | All Foundation stories are Done. The feature is live | Measuring |
| 9 | Verdict | On 20 Feb, Ana runs /ship-review. It reads the actual numbers: flag use is 41% against a target of 30%; the guardrail held. It writes a 3-line verdict at the top of the PRD and posts the last project update | Done |
During the build, the project lead posts a short project update each week. /eod-sync drafts it.
Variations
- Small work. Less than about one sprint, one team, no pricing or data change:
/prdwrites a one-page brief. The rest of the flow is the same. - A bug or a debt item. No PRD and no brief. It is an issue in a standing project with the label
No-PRD. - Scope changes during the build. Change the PRD first and log the change in §11. Then change the stories.
- A second phase. Add a milestone and run
/to-issuesfor it. Same PRD, same project. - New scope after shipping. A new project with
/ V02and a new PRD that links the first one. A shipped PRD does not change. - Two tracks with different leads. One project per track with the label
Track. The PRD is on the lead track's project. - A request arrives from outside (a client message, a bug report). It goes to Triage. Someone accepts it into a project or declines it.