Guide
From guide/humea-product-development-guide.md#4 · v1.4 · 2026-11-18
4. Rules
The rules of the system, each with the reason for it.
Eight rules. Each is one thing to do, not a process to run.
- Not all work gets a PRD. If the work is less than about one sprint for one team, and it does not touch pricing, data or another team, write a brief: §1–§4 + §7 of the PRD template on one page, with the project label
Brief. Bugs and debt need neither. They go to a standing project with the labelNo-PRDas plain issues. Why: a heavy template for small work makes people stop using the system. - Definition of Ready. A story enters Todo only when it has:
Rids cited, acceptance criteria with at least one failure path, design states linked, events listed, the repo or surface named, a way to verify, and a named verifier. All other stories stay in Backlog. Why: a person or an agent can start a Todo story without a question. - Definition of Done. A story moves from Verify to Done only when someone other than the builder verified the acceptance criteria. An agent cannot verify its own work. Why: when builders close their own criteria, "done" loses its meaning.
- Weekly project update. The project lead posts a Linear project update each week that the project is in Building: on track, at risk or off track, plus three lines.
/eod-syncdrafts it. Why: this is the health signal for the business owner. No extra document, no meeting. - Ship review. When a project ships, it goes to Measuring. On the Metric check-in date, run
/ship-review. The project goes to Done when the verdict is in the PRD. Why: without a verdict, nobody learns if the bet worked. - Versioning. A shipped PRD is immutable. One exception: you can add a new row to §11. New scope = a new project
/ V02with a new PRD document that links the first one. A new phase on the same scope = a new milestone. The test: if the meaning of success changes (new goals, different metrics), it is a new version. Why: the verdict must refer to a PRD that did not change after the fact. - Evidence cites research. Observed evidence in PRD §2 cites a research ID from
humea-research-center(study, nugget or pattern). Why: a claim is one step away from its source. - Agents work as delegates. A person is always the assignee of an issue. An agent starts only from Todo. An agent plans first; the assignee accepts the plan. Only a person moves a story to Done. An agent does not change scope, priority or an approved PRD. Why: accountability stays with a person, and verification stays independent.
Three more rules keep the structure correct:
- One PRD, one project. Phases are milestones. If the project description and the PRD disagree, the PRD wins.
- A PRD moves to Ready only when its reviewers signed off and no open question in §11 blocks the build.
- A project without a PRD document is an error, unless it has the label
No-PRD.
Not used for now (the cost is higher than the value at this team size): story-point estimation, formal RICE or ICE scoring, OKR cascades, RFC processes and a separate roadmap tool. Linear initiatives and project views answer "what happens now and what is next". Look at this again if the team doubles.